acquired in next six months.” He said the
                                                                         work of acquiring the land is in advanced
                                                                         stage and it will be available for the pro-
                                                                         ject soon.
                                                                           The chairman said that a total of 1,380
                                                                         hectare land is required for the project,
                                                                         out of which railways has acquired 479
                                                                         hectare from the  private persons and 119
                                                                         hectare from government land. He also
                                                                         said that once the 90 per cent of land is
                                                                         acquired, six out of 29 tender packages
                                                                         for the project will be out in the month
                                                                         of March and April this year. Yadav also
                                                                         stressed that theNational High Speed
                                                                         Rail Corporation Limited (NHSRCL) will



                                                                          The Ahmedabad-Mumbai
                                                                          bullet train is a visionary
      future development of other High-Speed   commitment of Rs 1.10 lakh crore to exe-
      Corridors in India.              cute the project. Interestingly, Thackeray   project that will
        In addition, 300 young officials of    had likened the bullet train project to a
      Indian Railways are being trained in    “white elephant”, saying a decision on it   herald a new era of safety,
      Japan to give them exposure in high   will be taken only after he is convinced
      Speed Track Technology. Keeping in view   it will boost industrial development of   speed and service for the
      the long-term plan for human resource   the state.
      development, Government of Japan has   Apart from the Centre’s contribution,   people and help Indian
      also offered 20 seats per year for Master’s   there is also a move to get  5,000 crore
      course from the universities of Japan, for   from states of Maharashtra and Guja-  Railways become an
      serving Indian Railway officials. This pro-  rat, which own a fourth of equity in the
      gramme is fully funded by Government   project, in the form of extra budgetary   international leader in
      of Japan.                        resources (EBR), the Western Railway’s
                                       ‘Pink Book’ said.                    scale, speed and skills
      Current status of project           It can be noted that in FY20, the two
      Even as Maharashtra Chief Minister    states collectively contributed  1,000
      Uddhav Thackeray has questioned the   crore in EBR towards the project. The
      high costs and feasibility of the bullet   Japan International Cooperation Agency
      train project, it has now emerged that   (JICA) has made a soft loan commitment   be able to complete the project before its
      the Union Government has allotted    of  1.10 lakh crore to execute the project.  deadline of December 2023.
      5,600 crore for the ambitious project   The Union government-controlled   He said that the project will be com-
      for fiscal 2020-21. Sources in the National   Indian Railways has a 50 per cent equity   plete in three phases and the first phase
      High-Speed Rail Corporation said a pro-  stake in the project. In her budget speech   of 50 km stretch will be completed by
      vision of  5,600 crore has been made for   last Saturday, Union Finance Minister   August 2022. According to NHSRCL, the
      the 500-km rail project, modelled on the   Nirmala Sitharaman highlighted that the   tender for design and construction of
      lines of Japan’s famous bullet train.  high-speed train between Mumbai and   civil and building works, including test-
        Apart from the Centre’s contribution,   Ahmedabad would be “actively pursued”.  ing and commissioning of 237 km length
      there is also a move to get  5,000 crore   About 47 per cent of land for bullet   of mainline out of elevated 460 km,
      from Maharashtra and Gujarat, which   train project have by now been acquired.   has been floated. The mainline has one
      own a fourth of equity in the project, in   The Railway Board Chairman V.K. Yadav   mountain tunnel of about 280 metre, 24
      the form of extra budgetary resources   said, “Till date 47 per cent of the land   river crossings and 30 road and canal
      (EBR), the Western Railway’s “Pink Book”   has been acquired for the 508-km long   crossings.
      said. The Japan International Coopera-  Ahmedabad-Mumbai high speed rail
      tion Agency (JICA) has made a soft loan   project, and rest of the 53 per cent will be   letters@tehelka.com