MEGA STORY: HIGHWAYS OF HYPE

M. Riyaz Hashmi
If some motorists on the Lucknow-Kanpur Expressway had not applied their brakes in time, they could have ended up in a pit along with their vehicles. Why? The road, built barely 12 days earlier, had sunk. This is the same expressway that Road Transport and Highways Minister Nitin Gadkari had claimed was better than American roads. Tehelka examined cases linked to seven major road projects involving a combined cost of nearly `1.6 lakh crore. The technical reasons vary- from weak and highly plastic soil and incomplete drainage systems to prior objections over construction quality, rutting on newly built roads and landslides in difficult hilly terrain.

1. Lucknow-Kanpur Expressway:Cracks 12 Days After Inauguration, Major Slippage in 13 Days
PNC Infratech Limited is the construction company for this 63-kilometre project, costing around ₹4,200 crore. In June 2024, the CBI registered an FIR against the company under the Prevention of Corruption Act. Subsequently, the Ministry of Road Transport and Highways debarred the company and two of its SPVs from tendering for one year, which was reduced to four months in February 2025.
The political context linked to PNC also includes Naveen Jain. He was formerly a whole-time director of the company, served as Agra Mayor in 2017 and became a Rajya Sabha member from Uttar Pradesh in 2024. His brother Pradeep Kumar Jain is the company’s Chairman and Managing Director.
On July 13, 2026, Rajnath Singh, Nitin Gadkari and Yogi Adityanath dedicated the expressway to the nation. Exactly 12 days later, on July 25, photographs of cracks and subsidence emerged. Experts from IIT Kharagpur were brought in for a technical investigation.
The preliminary investigation did not find any major deficiency in the thickness or material of the upper layer that could directly be described as “substandard asphalt”. Instead, indications emerged of weak and highly plastic soil and drainage-related problems. On August 5, NHAI initiated the process of declaring PNC a non-performer and stopping its participation in future projects. It also emerged that repairs to the affected stretch would be carried out at the company’s cost and that action would be initiated against the concerned officials and the independent engineering agency.
Interestingly, on July 16- 10 days before the major slippage- PNC had signed concession agreements for two new HAM projects in Uttar Pradesh. The combined bid project cost of the two projects was ₹3,483 crore.


2. Ram Van Gaman Path: Road Sinks Before Inauguration
The Shringverpur section is linked to Ram Van Gaman Path Private Limited, whose SPV structure is associated with S&P Infrastructure Developers Private Limited and Sunny Infraprojects Private Limited. In 2019, NHIDCL debarred S&P for two years. The company challenged the decision in the Delhi High Court, and on July 1, 2019, the court cancelled the debarment. The court held that the alleged lapses were not sufficient grounds for blacklisting. This old dispute does not establish anything about the quality of the current road, but it forms part of the company’s background.
Now come to Shringverpur. This section of the approximately 210-kilometre Ram Van Gaman Path, estimated to cost around ₹4,400 crore, is still under construction. Following September rains, cracks and subsidence appeared on the newly constructed road near Shringverpur Dham in Prayagraj.
Initial reports indicated damage at four locations within a stretch of around 100 metres; subsequent government responses put the length of two affected stretches at 300 metres and 150 metres. Officials cited rainfall and soil erosion as the immediate causes and issued a notice to the contractor, following which repairs were initiated.
The question that remains unanswered is: if rainfall caused the road to settle, why had the water flow not been adequately managed in advance? And if the soil was weak, why was this risk not detected earlier during quality checks of the under-construction road?


3. Delhi-Dehradun Economic Corridor: First Subsidence 79 Days After Inauguration

The contract for the approximately 29.5-kilometre package from Km 27.000 to Km 56.500 is with Krishna Constructions, with a bid value of around ₹503 crore.
In an Income Tax-related case involving the company, an Income Tax Appellate Tribunal order of December 2024 referred to liabilities of around ₹52 crore detected during a 2016 search, which were subsequently admitted as undisclosed income. No direct connection between this case and any irregularity in road construction has been established, but it forms part of the company’s background.
On April 14, 2026, Prime Minister Narendra Modi inaugurated the approximately 213-kilometre Delhi-Dehradun Economic Corridor, costing more than ₹12,000 crore.
Rainfall occurred on the night of July 2, and 79 days later, in the evening, a section of the newly built road sank at Gogwan Jalalpur in Shamli.
The NHAI explanation makes the story even more interesting. According to the authority, water accumulated and the permanent cross-drainage system could not become fully operational. Local opposition had obstructed the installation of culverts, while slope protection and chute-drain work remained pending because of land-related disputes. The project had also taken around 13 months longer than its original timeline.
After repairs, an approximately 1.5-kilometre interim drain was constructed and the slope up to Km 56+500 was redesigned. Following the incident, notices were issued to the Project Director, authority engineers and the construction agency.
The story did not end there. Cracks in the side wall of a bridge at Biharigarh in Saharanpur, cavities beneath the road in Baghpat and soil erosion in other parts of Saharanpur were also reported. Nevertheless, NHAI conducted core-cutting and pavement-layer tests at 23 locations.


4. Ganga Expressway: Repeated Damage in the Same Area 111 Days After Inauguration
The affected stretch in Unnao falls under Group-III, awarded to Adani Enterprises Limited. The group has a length of 155.7 kilometres, and according to records of Patel Infrastructure Limited, the value of its EPC work is around ₹4,732.57 crore. Adani Road and Transport Limited also has a role in the construction chain.
Patel Infrastructure made two contributions of ₹1 crore each to the BJP during financial year 2024-25, totalling ₹2 crore. This does not constitute evidence of favouritism or quid pro quo in any contract. Older contract-related disputes involving the company are also not directly connected to the quality of the current road, but they are part of the background of the public project.
Now to the road itself. The 594-kilometre Ganga Expressway, costing around ₹36,230 crore, was inaugurated by Prime Minister Narendra Modi in Hardoi on April 29, 2026. On August 18- 111 days later- near the Sarai Katian canal bridge at Km 421-422 in Unnao, rainwater washed away soil along the roadside and a section of the road settled. But in this case, the repeated damage is more significant than a single incident. In early July, the approach road was affected. In August, the embankment of the main carriageway was affected. Later, cracks appeared in the repaired section and subsidence was reported near the service connection around Km 423.6.
The technical record is the most important aspect here. Original documents reportedly contain NCRs raised by the independent engineer concerning embankment compaction and ground-improvement work.
If these objections questioned the quality of embankment or ground-strengthening work, how was independent verification carried out after rectification? And how deeply did the investigation go after the first damage in July? Rain may have been the immediate cause, but the question is whether the quality risks recorded before opening the road were actually eliminated- or merely closed on paper.

5. Delhi-Mumbai Expressway: Rutting Over Seven Kilometres on a New Road, Contract Terminated
Package-10 in Sawai Madhopur was awarded to Dhaya Maju Infrastructure (Asia) Sdn. Bhd.–Crescent EPC Projects & Technical Services Limited JV. The approximately 26.5-kilometre package had a contract value of ₹905.32 crore. In July 2026, litigation concerning the package between the JV and NHAI also came before the Delhi High Court. The dispute had therefore moved beyond technical issues to the contractual level.
This stretch was opened to traffic in February 2026. Soon afterwards, pavement distress and rutting were reported over stretches of approximately 4 kilometres and 3 kilometres- around 7 kilometres in total. In April, NHAI terminated the contract, stopped the remaining work from April 21 and decided to undertake rectification at the risk and cost of the previous contractor.
NHAI constituted an independent technical expert committee and collected samples from the affected road. The final cause remains a matter of investigation.


6. Sambalpur-Cuttack NH-55: Road Subsidence, Cracks in Flyover and Repairs Needed at 270 Locations
The flyover at Rairakhol is linked to an approximately two-kilometre, six-lane flyover project awarded to Agrawal Infrabuild Private Limited (AIPL). The recorded cost is around ₹106.32 crore. After cracks appeared, NHAI issued notices to the contractor and project engineer and ordered a structural audit. Now consider the sequence of events on this corridor.
Photographs of cracks in the flyover built over an elephant corridor near Rairakhol in Sambalpur emerged in June 2026. The structure had been opened to traffic only around six months earlier. Before that, a section of the road near Pradhanpali Chowk had already sunk. In August, around 270 works requiring rectification were identified on the Sambalpur-Angul stretch. Questions were raised about the use and compaction of fly ash. There were also concerns that prolonged rainfall could cause fly ash to wash away, potentially creating cavities beneath the road. According to a response by the Ministry of Road Transport and Highways in the Rajya Sabha, the cost of Cuttack-Angul Package-1 was ₹1,108.62 crore, Package-2 was ₹1,109.80 crore, and the Angul-Sambalpur section cost ₹2,514.07 crore- totalling around ₹4,732.49 crore.


7. Mumbai-Pune Expressway Missing Link: Mountain Slipped 66 Days After Inauguration
The package involving the main tunnels was executed by Navayuga Engineering Company Limited, which also has a role in the subsequent rockfall protection arrangements.
According to available electoral bond records, the company purchased bonds worth a total of ₹55 crore. As per available records, the entire amount went to the BJP- ₹45 crore in 2019 and ₹10 crore in 2022.
This donation does not constitute evidence of any improper benefit or quid pro quo. However, it is relevant in the context of transparency in contracting, quality certification and independent monitoring of public projects. Navayuga had also remained in the spotlight following the Silkyara-Barkot tunnel incident. While no direct connection between those events and the technical issue on the Missing Link has been established, they form part of the company’s history. MSRDC said that the tunnel had not suffered structural damage and that the incident was a natural landslide caused by heavy rainfall.
However, following the incident, work began on altering water pathways above the hill, removing loose rocks, installing steel bolts and high-tensile steel mesh, and putting up steel barriers to prevent large rocks from falling. Rockfall protection is being undertaken across an area of approximately 1.38 hectares, with the target of completing the work by the end of October 2026.

Roads Survive Abroad, But in India, the System and Independent Oversight Remain the Bigger Questions

These seven cases do not lead to the conclusion that India lacks rules for road construction.
The Indian Roads Congress, the Ministry of Road Transport and Highways and NHAI have detailed standards covering design, materials, compaction, drainage, pavement, quality control, independent engineering supervision and defect liability. The existing system includes quality control by the construction company, supervision by the authority/independent engineer and approval by NHAI. During the defect liability period, the contractor is also responsible for rectifying defects.
But if an embankment, drainage system, pavement or hill-protection system develops problems soon after a road is opened, how often is the entire chain- from construction to certification- independently investigated? The Federal Highway Administration’s quality assurance model in the United States places emphasis not only on the contractor’s quality control and government approval but also on independent assurance. In other words, it is not enough to verify that the contractor conducted a test; the reliability of the testing and its data must also be independently assessed. There, an asset-management framework connects roads, bridges, safety, maintenance and investment across the entire life cycle. In Britain, safety, maintenance and long-term performance are central objectives for the strategic road network, while institutions such as the Office of Rail and Road independently monitor the performance of National Highways.
In France and Europe, drainage, earthworks and the strength of the ground beneath roads are considered together during design. Road safety audits provide a mechanism for identifying risks from the design stage until a road is opened. In China, highway quality inspection involves separate roles for construction, supervision, testing and government oversight. In Dubai, road conditions undergo regular technical assessment along with preventive and predictive maintenance. Qatar places emphasis on sampling, laboratories, calibration and traceability of test data. Saudi Arabia’s highway code also takes a full life-cycle approach- from planning to maintenance.


The Same Companies Keep Appearing in Highway Contracts: The Question Is Not Just About Quality

In its investigation, Tehelka examined 221 major infrastructure projects across the country alongside available tender and award details. A second aspect emerged: the market for major highway and expressway construction appears increasingly concentrated among a select group of companies. In the Pune Ring Road, Jalna-Nanded Expressway and Virar-Alibaug Multi-Modal Corridor in Maharashtra, names such as Megha Engineering, Navayuga, PNC Infratech, GR Infraprojects, Afcons, Patel Infrastructure, L&T, J Kumar, NCC, APCO, Montecarlo, HG Infra and Welspun appeared repeatedly in application records for 2023-24. Across the three projects, 28 companies applied and 18 were found technically qualified. In the first nine packages of the Pune Ring Road, against an estimated cost of around ₹16,618 crore, the L-1 bids totalled around ₹22,800 crore- approximately 37 per cent higher.
Megha Engineering and Navayuga secured L-1 in three packages each. Subsequently, two packages were awarded to Afcons, whose combined L-1 bid was around ₹4,787 crore.
In the six packages of Jalna-Nanded, APCO secured L-1 in two, Montecarlo in two, while PNC and Roadway Solutions secured one package each. Against an estimated cost of around ₹11,442 crore, their L-1 bids totalled around ₹15,465 crore.
In Nagpur-Gondia, Afcons, Patel and NCC appeared again, while in Nagpur-Chandrapur, names such as GR Infra, Gawar, HG Infra and BSCPL emerged. In a major package in Bhandara-Gadchiroli, Patel Infrastructure emerged as L-1. Across these five Maharashtra projects, the available packages rose from an estimated ₹47,000 crore to L-1 bids of more than ₹63,500 crore. Independent financial research also puts the award figure at around ₹63,600 crore.
The subsequently cancelled Virar-Alibaug packages are not included in this figure. In Virar-Alibaug, 11 initial construction contracts worth around ₹26,300 crore had been awarded to seven companies. However, following questions over high bids and financial viability, there was consideration of cancelling them and taking the project forward under a different model.
This raises questions about the gap between the estimated DPR cost, market bids and the government’s final financial commitment.
The fact that the same company succeeds in multiple projects is not, by itself, evidence of wrongdoing or collusion. Companies possessing the technical capability, financial strength, machinery and experience required for large road projects are limited in number.
The real question is how broad the competition is- and how much weight a company’s previous performance carries in its next bid.
Political donations also provide context. Electoral bond data linked to Megha Engineering amounts to around ₹966 crore, of which around ₹584 crore went to the BJP.
Bonds linked to Navayuga were worth around ₹55 crore, and available records show the entire amount going to the BJP. A BJP contribution of around ₹5 crore linked to GR Infraprojects is also recorded. Calling these donations payments made in exchange for contracts or evidence of political protection would go beyond the facts. The significance lies in the question of why the timelines of contracts and political donations should not be a matter of public scrutiny when the same corporate groups repeatedly appear in public projects worth thousands of crores.
In the case of Megha Engineering, the short time gap between electoral bonds linked to the company and some major public projects draws attention.
The CBI also registered an FIR against the company in 2024. Similarly, the CBI action and temporary debarment involving PNC are part of its record. The larger question emerging from the 221 projects is whether the highway construction system has become so dependent on the expertise of a few established companies that accountability weakens once contracts are awarded.
If one company is handling projects worth several thousand crores, how much weight should its previous quality record, defects, penalties, independent engineer’s objections and maintenance performance carry in subsequent bids?

Questions Sent to Companies and NHAI, Responses Awaited
As part of this investigation, Tehelka sent detailed questions by email to the private companies, contractors, concessionaires and construction agencies whose roles emerged in the projects examined.
The questions concerned construction quality, technical investigations, independent engineers, recorded objections, repairs and contractual responsibility.
PNC Infratech was asked about the cracks on the Lucknow-Kanpur Expressway, the approximately 300-metre slippage, preliminary findings regarding weak soil and drainage, and quality tests conducted before the road was opened.
S&P Infrastructure Developers was asked about subsidence at Shringverpur, rainfall, soil erosion, construction and drainage quality and repairs.
Krishna Constructions was asked about incomplete permanent drainage, culverts, slope protection and subsequent corrective work on the Delhi-Dehradun corridor.
Adani Road and Transport Limited, Adani Enterprises and Patel Infrastructure were asked about repeated damage on the Unnao section of the Ganga Expressway and the resolution of objections relating to embankment and ground-improvement work.
Dhaya Maju-Crescent EPC JV was asked for its response regarding around seven kilometres of rutting on the Delhi-Mumbai Expressway, quality testing, termination of the contract and the investigation by the expert committee.
Agrawal Infrabuild Private Limited was asked about cracks in the Rairakhol flyover, construction and quality testing, and the notice issued by NHAI. Project Engineer L.N. Malviya was asked for his response regarding his supervisory role. Navayuga Engineering was asked about the landslide near Tunnel-2 of the Mumbai-Pune Expressway Missing Link, the original geotechnical and rockfall safety assessments, and the additional safety work being undertaken after the IIT-Bombay review. NHAI was also sent brief and specific questions seeking its response on the technical deficiencies that emerged in all seven projects, quality testing, independent monitoring, contractor accountability and action taken.
Till the time of publication of this story, no detailed response had been received from NHAI or any of the concerned companies or agencies.
If responses are received, Tehelka will publish them with the full context and the relevant questions. The objective is not to hold any company or agency guilty, but to bring into the public domain the entire chain of construction, quality testing, independent monitoring and accountability in public projects.


Infrastructure Needs Durability and Quality, Not Just Showmanship:
Raghav Chandra, Former Chairman, National Highways Authority of India (NHAI)


India has witnessed rapid expansion of infrastructure, but serious questions are being raised about quality and durability amid efforts to complete projects quickly. Incidents of road subsidence, cracks, surface displacement and other problems have emerged on several projects, including the Lucknow-Kanpur, Ganga, Delhi-Dehradun and Delhi-Mumbai expressways. The economic losses caused by such incidents are significant, but the damage they cause to public confidence between citizens and the government is far greater. Such incidents can result from inadequate geotechnical investigations, neglect of ground-improvement measures, insufficient drainage and technologies unsuitable for local geographical conditions. A weak supervisory arrangement among designers, construction companies, independent engineers and NHAI field officials can also be a major factor. When something goes wrong, accountability often remains unclear. Detailed project reports and ground assessments should be made the backbone of every project. However, in some cases, old project reports are used as the basis for preparing new DPRs with only minor modifications. The role of independent engineers is also critical, but they must be given adequate authority and capacity to stop a project, flag serious risks and ensure necessary design changes. The system of awarding government tenders to the lowest bidder can also affect quality. A contractor quoting an extremely low bid may come under pressure to recover costs and could cut corners in materials, ground investigations or construction quality. Therefore, responsibilities for design, construction and supervision should be clearly defined and separated.

Ground Report

Pathankot-Mandi Highway Pockmarked with Potholes
Charanjit Ahuja / Maninder Singh

For travellers using National Highway-154 between Pathankot and Mandi, travelling through several stretches has now become a test of patience and caution. Potholes filled with rainwater, broken asphalt, mud and damaged road edges have turned several sections of the highway into accident-prone zones.
The situation becomes even more dangerous during the monsoon and particularly after sunset.
In Jogindernagar town, the condition of the highway is particularly poor around Laxmi Bazaar, Pathankot Chowk and Sai Bazaar.


In several places, the upper road layer has peeled off, leaving deep potholes.
Motorists, especially two-wheeler riders, have to navigate these potholes with extreme caution.
According to local traders near the post office, a pothole around one foot deep has become a serious hazard.
Traders Gyan Chand, Ramesh, Ajay and Vinod Kumar said several two-wheeler riders had lost control after their vehicles entered the pothole, resulting in accidents.
A similar situation exists at Pathankot Chowk, where deep potholes pose a danger to vehicles.
Near the police station, a section of the road has separated from the tarred surface, creating difficulties not only for motorists but also for pedestrians.
A similar situation exists on the Chogan-Khushinagar stretch of the highway in Nurpur.
Continuous monsoon rainfall has further deteriorated the road, with several damaged stretches turning into muddy, waterlogged areas.
Travellers and shopkeepers living along the highway say two-wheeler riders face the greatest risk.
According to some residents, two-wheeler riders have been involved in accidents because they could not judge the depth of water-filled potholes in the dark.
Concerned over the deteriorating condition of the road, shopkeepers recently staged a protest, led by the local non-government organisation Nurpur Sudhar Sabha, against the construction company working for the National Highways Authority of India.
The company is constructing the first phase of the Pathankot-Mandi four-lane project between Kandwal and Bherkhud.
With no immediate relief, some shopkeepers have started filling potholes outside their establishments themselves.
The shopkeepers allege that Mumbai-based IRB Infrastructure Developers, which is constructing the highway project, has sublet part of the work to another road construction agency.
They allege that the agency has failed to address the problems faced by local residents and travellers during construction of the bypass.
Another problem has made the situation more serious in Chogan Bazaar.
Shopkeepers say the old water drain at the entrance to the market from the Niazpur side has been blocked by debris and silt generated during hill cutting for the bypass.
As a result, rainwater and mud flow onto the highway, creating potholes and increasing their size.
To keep Nurpur town outside the new four-lane alignment, NHAI is constructing a bypass from Bodh to Khushinagar.
However, the existing highway passing through suburban areas between Bodh and Khushinagar remains in poor condition and requires immediate repair and maintenance.
The poor condition of the old highway is not limited to Nurpur and Jogindernagar.
NHAI has changed the alignment of nearly half of the 208-kilometre Pathankot-Mandi Highway.
Despite this, thousands of vehicles continue to use the existing road every day.
NHAI had planned a new alignment for the approximately 60-kilometre Paror-Padhar section.
Similarly, the alignment between Rajol and Nagrota Bagwan has also been changed over around 30 kilometres. As a result, around 100 kilometres of the existing highway may not form part of the proposed four-lane alignment. However, the old road continues to carry heavy traffic. Travellers say its poor condition becomes particularly concerning during the monsoon. During this period, potholes become submerged in water and damaged road edges deteriorate further.
The condition of bridges is another concern. More than 20 small and large bridges on the old highway require attention. Several of these bridges date back to the British era.
Work to replace them with new bridges or undertake major repairs has yet to begin.
A senior Public Works Department (PWD) official said the state government had transferred the highway to NHAI through a notification and that NHAI was responsible for maintaining both the existing and new highways.

Road Widening and the Risk of Landslides
Given the widespread threat of landslides on mountain roads during the monsoon, the condition of the highway also needs to be understood in this context.
A study conducted by the Department of Geography at Himachal Pradesh University states that unscientific cutting of mountains during road construction and widening can loosen soil and destabilise upper portions of slopes.
During the monsoon, water penetrating into such slopes can make them even weaker, increasing the likelihood of landslides and falling rocks. The Sarkaghat-Jogindernagar road, an important route for residents of Jogindernagar, Sarkaghat and Dharampur, has also been affected by landslides and rainfall.
The study states that widening work has further worsened the condition of the Dharampur-Jogindernagar section and that a 12-kilometre stretch of the road has become vulnerable to landslides.
Several villages- including Basahi, Chhakka, Chirah, Chimnu and Neri- were identified as vulnerable areas along the roadside.
At these locations, large stones and pieces of rock were reported to have slipped down slopes following hill cutting.
Near Chhakka village, a grassland subsided after a slope weakened during road widening.
During the monsoon, water also entered the affected area.
Similarly, near Chirah, Basahi and Chimnu villages, large quantities of soil came down after cutting was carried out at the base of slopes.
This damaged the road and vegetation.
The study also recorded landslides on the link road connecting the Shimla-Karsog Highway near Bhalog village and on the Shala link road near Barjohdu in Gohar block.
In the latter case, the absence of a retaining wall was identified as one of the causes.
During the monsoon, landslides damaged around 50 metres of road.
Unconsolidated debris sliding down slopes during or immediately after heavy rainfall was also observed near Bahi and Kufru-Mochakka villages in Chunjatra block, Kotla village in Dharampur block and Harabag village in Drang block.

NHAI Assures Repairs
NHAI officials say repairs in Jogindernagar have been approved and work will begin as soon as weather conditions improve.
NHAI site engineer Ankit said: “Repair of the damaged section of the highway in Jogindernagar town will be carried out soon. Work could not begin because of bad weather. As soon as weather conditions become favourable, laying of asphalt will begin immediately.”